What action should the Project Manager take regarding the remaining windows?
- A . All requirements that have not been met are automatically carried over to the next increment.
- B . Extend the time allocated to Timebox C, to allow time to complete these.
- C . Insist that all available resources within the Solution Development Team are redirected to this work over the remaining two days.
- D . Decompose the individual elements of work to be completed on the windows and reprioritise them to meet the Minimum Usable Subset.
What action should the Project Manager take regarding the remaining windows?
- A . All requirements that have not been met are automatically carried over to the next increment.
- B . Extend the time allocated to Timebox C, to allow time to complete these.
- C . Insist that all available resources within the Solution Development Team are redirected to this work over the remaining two days.
- D . Decompose the individual elements of work to be completed on the windows and reprioritise them to meet the Minimum Usable Subset.
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?
- A . Is good at quietly implementing directions without challenging decisions at every step.
- B . Is well-positioned to bring together other line leaders facing similar change situations.
- C . Has a strong network due to supporting all staff at all levels organization-wide.
- D . Has direct line authority over the staff who will be changing internal IT systems.
- E . Wants to gain experience in change management to improve future implementations of IT systems.
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
- A . The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.
- B . The Solution Development Team should commence understanding and delivering the new requirement.
- C . The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels‘ Senior Management Team.
- D . The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
- A . The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.
- B . The Solution Development Team should commence understanding and delivering the new requirement.
- C . The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels‘ Senior Management Team.
- D . The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.
For cognitive learning, which is the BEST example of providing ‚learning feedback‘?
- A . Giving supervisor feedback on return to work.
- B . Testing before and after learning.
- C . Reviewing learners’ ideas in a group discussion.
- D . Discussion at the learners‘ next annual performance reviews.
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
- A . Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.
- B . Hold a separate Daily Stand-up meeting for contractors only.
- C . Provide a detailed plan of activity for each contractor team.
- D . Schedule the electrical and plumbing teams so that they work on different Timeboxes.
Access a podcast to learn more about the principles of reviewing performance in staff appraisal.
Access a podcast to learn more about the principles of reviewing performance in staff appraisal.
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?
- A . Focus on the business need.
- B . Deliver on time.
- C . Collaborate.
- D . Never compromise quality.