Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
- A . Ask the Team Leader to resolve the situation.
- B . Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.
- C . Remove empowerment from the Solution Development Team.
- D . What action should the Project Manager take when dealing with the Solution Development Team’s argument that the windows should not be a Must Have priority?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
- A . Ask the Team Leader to resolve the situation.
- B . Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.
- C . Remove empowerment from the Solution Development Team.
- D . What action should the Project Manager take when dealing with the Solution Development Team’s argument that the windows should not be a Must Have priority?
Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do not happen again.
Which Agile principle MOST influences this course of action?
- A . Focus on the business need.
- B . Deliver on time.
- C . Build incrementally from firm foundations.
- D . Demonstrate control.
Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time.
What action should the Project Manager take?
- A . Change the end date of the Timebox.
- B . Ensure that this issue is escalated to the project level roles.
- C . Amend the end date in the Delivery Plan.
- D . Accept that the Must Have requirements will not be delivered on time.
Which 2 individuals would be suitable for the role of Workshop Facilitator?
- A . Team Leader
- B . IT Operations Manager
- C . Marketing Director
- D . Software Developer
- E . Project Manager
Which 2 individuals would be suitable for the role of Workshop Facilitator?
- A . Team Leader
- B . IT Operations Manager
- C . Marketing Director
- D . Software Developer
- E . Project Manager
Which 2 individuals would be suitable for the role of Workshop Facilitator?
- A . Team Leader
- B . IT Operations Manager
- C . Marketing Director
- D . Software Developer
- E . Project Manager
Which is the BEST reason to remind learners of related knowledge or skill they already possess?
- A . Enables learners to understand how they learn.
- B . Helps learners plan to use immediately what they learn.
- C . Increases learners’ understanding of what the new learning will enable them to do.
- D . Reduces learners’ concerns about new learning.
Which is the BEST reason to remind learners of related knowledge or skill they already possess?
- A . Enables learners to understand how they learn.
- B . Helps learners plan to use immediately what they learn.
- C . Increases learners’ understanding of what the new learning will enable them to do.
- D . Reduces learners’ concerns about new learning.
Which statement should be recorded under the Lessons from previous change initiatives heading?
- A . UniCo has always been seen in the marketplace as being traditional and cautious.
- B . UniCo has always successfully used customer journey mapping for educating staff in customer needs.
- C . A new software development platform is needed to integrate the new services into operational processes.
- D . The renewal of the lease for the office housing Selco staff is due in fifteen months’ time.