A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted.
Which of the following did the team perform?
- A . Regression testing
- B . Smoke testing
- C . Stress testing
- D . Automation testing
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter.
Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
- A . Compromising
- B . Forcing
- C . Smoothing
- D . Collaborating
After a migration was completed and a financial system was deployed, users have been unable to issue payment orders.
Which of the following should be implemented?
- A . Rollback plan
- B . Release plan
- C . Deployment plan
- D . Contingency plan
While working with a contractor, the project manager identified a communication conflict. The contractor did not agree that there was an issue.
Which of the following should the project manager and contractor review?
- A . Scope of work
- B . Request for proposal
- C . Vendor rules of engagement
- D . Project schedule
A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities.
Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?
- A . Create a list of tasks and share it with the team.
- B . Resend the scope of work to the team.
- C . Review the Gantt chart weekly with the team.
- D . Have the project sponsor meet with the team.
A project manager and team are currently in the planning phase of a project.
Which of the following should the team do during this phase?
- A . Identify and assess stakeholders.
- B . Hold daily status meetings.
- C . Remove access and plan the project sign-off.
- D . Review assumptions and constraints for input to the risk register.
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects.
Which of the following tools should the project team use to find the cause?
- A . Kanban board
- B . Pareto chart
- C . Ishikawa diagram
- D . Decision tree
A project team is developing an application that will allocate a building’s parking spaces. The building owner does not agree with using corporate colors in the application and has blocked
the release of the beta version for testing.
Which of the following best describes what the project manager should have done in the initiation phase to prevent this issue?
- A . Review of existing artifacts
- B . Development of an issue log
- C . Identification and assessment of stakeholders
- D . Establishment of accepted communication channels
Which of the following best represents the project impact to a company’s brand value?
- A . The project is compliant with local and state laws and becomes the standard for new projects.
- B . The project promotes new initiatives to expand its benefit to other communities.
- C . The project exceeds the sales quota for the third quarter and raises the bar for next periods.
The project meets the expected milestones and finishes on time and within budget.
A project team is working remotely from different locations across the country. As part of a lessons-learned exercise, the project manager would like to identify the level of engagement among project team members.
Which of the following would be the best tool for the project manager to use?
- A . Meeting chat
- B . Email
- C . Real-time survey
- D . Whiteboard