A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?
- A . Lead architect
- B . Project sponsor
- C . Program manager
- D . Scrum master
Which of the following provides a layered approach to logging in to systems that contain an organization’s most valuable intellectual property?
- A . Remote access
- B . Password protection
- C . Multifactor authentication
- D . Virtual private network
During a stand-up meeting, a team member asks to include a change that an important stakeholder requested in the project board. This request is denied, and the team member has to go back to what was originally planned for the sprint.
Which of the following individuals should the stakeholder have asked to request the change instead of the team member?
- A . Architect
- B . Project sponsor
- C . Scrum master
- D . Product owner
Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product.
Which of the following documents should the project manager expedite first?
- A . RFI
- B . RFP
- C . RFQ
- D . RFB
A financial manager reports that several employees‘ allocations from the past month appear to be 200% even though they are only assigned to a particular project.
Which of the following could MOST likely be the cause of this issue?
- A . A project manager assigned the wrong resources.
- B . A project manager did not release the resources
- C . A project manager did not remove the system access.
- D . A project manager did not provide the project sign-off.
A project manager makes a company-wide announcement about the successful completion of a project and thanks team members.
Which of the following is the project manager doing?
- A . Bringing attention to the project sponsor
- B . Sharing lessons learned
- C . Collecting feedback
- D . Celebrating the team’s hard work
A project team gathers weekly to review its progress.
Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
- A . Status report
- B . Project plan
- C . Change log
- D . Meeting minutes
A project sponsor would like to develop a minimum viable product, but the requirements are not well defined.
Which of the following should the project sponsor use?
- A . Rational Unified Process
- B . Waterfall
- C . Agile
- D . DevOps
Which of the following cloud models is designed to provide compute, storage, and networking resources on demand?
- A . Software as a service
- B . Infrastructure as a service
- C . Data as a service
- D . Platform as a service
A critical business initiative introduced new processes and technology to the organization.
Which of the following approaches should be used to ensure the deliverables are increasingly adopted and leveraged by the organization over time?
- A . Creation of a social news forum
- B . Management directives to use the new system
- C . New user kickoff meeting
- D . Monthly feedback and training sessions