A principle states 80% of the issues are the result of 20% of the causes.
Which of the following types of diagrams is based on this principle?
- A . Pareto
- B . Scatter
- C . Network
- D . Fishbone
A project manager queries stakeholders to identify the right communication channel to be used during the project life cycle. After reviewing the responses, the project manager reports that 70% of the stakeholders prefer email communication, and the rest prefer face-to-face communication.
The project manager should update the stakeholder register with:
- A . the preferred sponsor’s communication channel.
- B . the preferred project manager’s communication channel.
- C . the preferred reported communication channel.
- D . email communication as the preferred communication channel.
A company that is implementing an updated version of its main product hired a new project manager to lead the project. Prior to the start of the project, the sponsor asked the project manager to prepare a report on the defects found in the previous project to avoid a decrease in production. The report shows that the two main defects are related to cosmetic and physical damage to the product.
Which of the following charts would BEST prioritize which defects to address?
- A . Pareto
- B . Run
- C . Control
- D . Histogram
Which of the following activities would be performed during the project closure phase when the waterfall methodology is being used? (Select two).
- A . Creating a backlog
- B . Managing the quality of deliverables
- C . Updating the issue log
- D . Performing a risk assessment
- E . Validating the deliverables
- F . Reconciling the project budget
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project.
Which of the following best describes this activity?
- A . Key stakeholder identification
- B . Preliminary procurement
- C . Solution design determination
- D . Critical factor enlistment
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
- A . Evaluating the project
- B . Releasing the resources
- C . Closing the contracts
- D . Reconciling the budget
SIMULATION
During a gate review meeting, the deliverable was rejected by the customer.
INSTRUCTIONS
Review the dashboard.
• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
• Part 2: Select the proper document(s) to be updated.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Part 1:
Part 2:
A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports.
Which of the following cloud models would the company suggest to the global franchise?
- A . laaS
- B . XaaS
- C . PaaS
- D . SaaS
When creating a project schedule, a project manager adds activities with zero duration.
Which of the following describes these types of activities?
- A . Critical paths
- B . Resources
- C . Milestones
- D . Work breakdown structures
During a status meeting for a multisystem program, a program manager learns that some deliverables from another project are delayed.
Which of the following should the program manager do next?
- A . Obtain details from the owner of the project.
- B . Update the critical path for the project.
- C . Apply contingency reserves.
- D . Reestimate epic user stories.