Which of the following software programs would be BEST to use lo store information related to business transactions?
- A . Record management system
- B . Customer relationship management
- C . Enterprise resource planning
- D . Content management system
A project manager was not part of a contract negotiation. The project manager is concerned that stakeholders will expect the project to achieve deliverables requested in the RFP.
Which of the following documents should the project manager produce FIRST to start communication about the boundaries of the project?
- A . Milestone chart
- B . Work breakdown structure
- C . Project charter
- D . Detailed scope statement
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter.
Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
- A . Compromising
- B . Forcing
- C . Smoothing
- D . Collaborating
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
- A . Based on the rule of seven, the process is under control
- B . The amount of data is insufficient to determine if quality is low.
- C . The process is out of control and should be revised.
- D . The goal should be adjusted since most of the data points are close to the lower limit.
Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect.
Which of the following actions should the project manager take NEXT?
- A . Escalate directly to the project sponsor
- B . Push the kickoff meeting out by one week
- C . Proceed with the kickoff as planned
- D . Identity replacements for project stakeholders
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals.
Which of the following plans is the project manager creating?
- A . Procurement
- B . Communication
- C . Quality assurance
- D . Risk
As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members.
Which of the following is the project team doing?
- A . Executing the approved contingency plan
- B . Constructing an Ishikawa diagram to determine the root cause
- C . Using a Pareto chart to prioritize the different causes
- D . Engaging the senior management team in regard to the issue
Which of the following activities are important parts of the closing phase? (Select two).
- A . Releasing resources
- B . Locking risks
- C . Updating stakeholder register
- D . Closing contracts
- E . Completing the work breakdown structure
- F . Negotiating the next project
A project sponsor is struggling to provide the latest project status information on a weekly executive call.
Which of the following should be reviewed?
- A . Meeting cadence
- B . Gap analysis
- C . Dashboard
- D . Adoption training
A project sponsor is struggling to provide the latest project status information on a weekly executive call.
Which of the following should be reviewed?
- A . Meeting cadence
- B . Gap analysis
- C . Dashboard
- D . Adoption training