A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase.
Which of the following types of testing should be done?
- A . Performance
- B . Smoke
- C . Regression
- D . Unit
A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project.
Which of the following should the project manager do next?
- A . Buy a replacement for the faulty equipment.
- B . Get the maintenance team to resolve the issue.
- C . Escalate the issue to the project sponsor.
- D . Rate the severity of the impact the issue has on the project.
A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards.
Which of the following should the project manager do?
- A . Train the team members.
- B . Assess the resource pool.
- C . Develop a QA plan.
- D . Create RACI matrix.
A PM is working on the schedule for a project that has technical tasks and requires a SME’s knowledge. The PM decides the best way to track this project is to have the project lead provide high-level updates.
Which of the following is the best tool to track this data?
- A . Gantt chart
- B . Project organization chart
- C . Program Evaluation Review Technique chart
- D . Milestone chart
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project.
Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
- A . Train users on the proper use of the system.
- B . Escalate the issue to the CCB
- C . Hold sessions to understand user challenges.
- D . Track system usage and report user activity.
- E . Log the issue in the project risk register.
- F . Create a memorandum of acceptable use.
A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed.
Which of the following steps should the Scrum team take next?
- A . Assign more resources to complete similar stories in the future.
- B . Break the stories into workable items that can be completed within one sprint.
- C . Extend the sprint duration when required with the approval of the product owner.
- D . Release the current progress into production and carry over the rest of the code for the next sprint.
Which of the following offers administrators more direct control over operating systems?
- A . Infrastructure as a service
- B . Software as a service
- C . Functions as a service
- D . Platform as a service
Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.
Select the Appropriate Tool:
Select the new critical path.
Option A
Option B
Option C
Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter.
Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?
- A . Compromising
- B . Forcing
- C . Smoothing
- D . Collaborating
A vendor manager communicates to the project manager that a shipment of new devices required for the completion of a project is delayed. The supplier is planning to deliver the devices two months after the agreed-upon date.
Which of the following should the project manager do first?
- A . Hold the project until the devices are delivered.
- B . Evaluate the impact to baselines.
- C . Request another supplier to ship devices.