Huawei H19-105_V2.0-ENU Übungsprüfungen
Zuletzt aktualisiert am 03.06.2025- Prüfungscode: H19-105_V2.0-ENU
- Prüfungsname: HCSA-Sales-Data Center Facility V2.0
- Zertifizierungsanbieter: Huawei
- Zuletzt aktualisiert am: 03.06.2025
The smoke sensors used in the NetEco6000 management system cannot replace the smoke sensors in the fire protection system.
- A . True
- B . False
HU is the smallest module with a capacity of 220kW under standard working conditions and cannot be split.
- A . True
- B . False
Three-proof paint coating can significantly reduce the failure rate of UPS in harsh environments such as salt spray, dust, high temperature and humidity, ensuring its service life in harsh environments.
- A . True
- B . False
The temperature cloud map temperature and humidity sensors are arranged in three layers, three in front and three in the back.
- A . True
- B . False
UPS products such as APM and NR need to be derated at 30 degrees Celsius, but UPS5000-E does not need to be derated below 40 degrees Celsius.
- A . True
- B . False
The UPS5000-S power module has a capacity of 50kVA and a height of 2U, with the highest power density in the industry.
- A . True
- B . False
UPS5000-A comes standard with an LCD display screen that supports multiple languages. It can display the system operating status in real time and can store up to () alarm records.
- A . 2000
- B . 2500
- C . 3000
If a customer wants to know the equipment availability and cabinet capacity, what function of NETECO should he use?
- A . Work Order Management
- B . Energy Efficiency Management
- C . Asset Management
- D . Capacity Management
UPS2000-G-(6K-20K) Maintenance Bypass Implementation Method ()
- A . Mainframe built-in maintenance bypass
- B . Optional PDU to support maintenance bypass
- C . Unable to support maintenance bypass
PDU8000 precision power distribution cabinet supports monitoring of phase current, active power, electric energy and branch switch status of each circuit.
- A . True
- B . False