A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort.
How should the business analyst (BA) handle the situation?
- A . Ask the project sponsor for additional funding
- B . Escalate the request to the project manager for reevaluation of the plan
- C . Spend the required effort to develop the detail
- D . Explain that the degree of effort may not be necessary at this stage
A new Chief Executive Officer (CEO) is appointed to revive a chain of well-recognized superstores. The CEO wants to increase sales by introducing on-line shopping. Most stores are understaffed and maintenance is a challenge.
Which of the following would be considered an asset?
- A . Store maintenance expenses
- B . Brand reputation
- C . Interest mounting on bank loan
- D . Online shopping website
A business analyst (BA) is negotiating and resolving conflict with stakeholders to ensure they participate in the required BA activities.
Which element of stakeholder management is the BA performing?
- A . Plan stakeholder engagement
- B . Monitor stakeholder engagement
- C . Gain agreement on commitments
- D . Confirm elicitation results
The business analyst (BA) has traced the requirements for the interaction between a customer and the new online ordering system.
Besides enabling the BA to ensure quality of the requirements to stakeholders, tracing the requirements will also enable the BA to:
- A . show all of the decision points in the business process.
- B . illustrate the relationships between relevant requirements.
- C . capture all users that will be impacted by the project.
- D . detail the inner workings of the system being changed.
The Chief Information Officer (CIO) of a large financial services firm with many technology applications was formally reviewing all ongoing projects and noticed that the requirements were complex and difficult to follow. The CIO asks the business analyst (6A) what would improve the stakeholder’s ability to understand the requirements.
Which of the following will improve the requirements quality?
- A . Traceability matrices
- B . IEEE /ISO 29148 requirements standards
- C . Additional requirements attributes
- D . Matrix documentation formats
All of the following stakeholders participate in the prioritization of requirements except for which one?
- A . Project team
- B . Implementation subject matter expert
- C . Domain subject matter expert
- D . Project manager
When can changes to requirements occur in a business analysis planning and monitoring assignment?
- A . Changes to requirements can occur any time after the project’s change control system has been enacted.
- B . Changes to requirements can occur at any time.
- C . Change to requirements can occur any time before the project scope statement is created.
- D . Change to requirements can occur at any time before the key stakeholders approve the identified requirements.
A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases.
Which requirements attribute can the BA include to allocate the requirements to the proper phase?
- A . Status
- B . Author
- C . Priority
- D . Source
A lead business analyst (BA) has received negative feedback on the deliverables produced by BAs in the organization. A major concern was ambiguous requirements.
What technique will help ensure business analysis information is clear and understandable?
- A . Choose appropriate format to communicate requirements
- B . Align test scenarios with business needs
- C . Ensure all requirements are testable
- D . Use checklists for quality control
The business analyst (BA) is investigating techniques that would be appropriate for determining how and who uses data across the identified processes.
Which technique should the BA select?
- A . stakeholder list, map, or personas
- B . Data dictionary
- C . CRUD (Create, road, update, and delete) matrix
- D . Decision model