A business analyst (BA) is working on a set of tasks to establish a governance process for the project. The BA intends to identify who has authority and responsibility to propose changes, who should be involved in the change discussions, and how changes will be documented and communicated.
Which of the following are the inputs that would help the BA complete the task?
- A . Business analysis approach and stakeholder engagement approach
- B . Governance approach and stakeholder engagement approach
- C . Governance approach and business analysis approach
- D . Stakeholder engagement approach and information management approach
You are the business analyst for your organization. You are currently working with Susan on creating a model as part of the specify and model requirements process. Susan doesn’t understand why you need a model. You explain to Susan that a model is just a simplified representation of a complex reality that is useful for understanding that reality and making decisions regarding it. In fact, you tell Susan, model can do all of the following except one option.
Choose the option that model cannot do?
- A . Define the resources that will be needed on the project team
- B . Define boundaries for the business domain
- C . Describe a situation or problem
- D . Describe thought processes and action flows
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process.
You will need all of the following as inputs to the qualitative risk analysis process except for which one?
- A . Risk management plan
- B . Stakeholder register
- C . Project scope statement
- D . Risk register
When using a change-driven approach, the business analyst may create an initial list of high-level requirements for the initiative.
This high-level requirements list is also known as what term?
- A . Requirements envisioning
- B . Project scope
- C . Product scope
- D . Requirements foundation
A business analyst (BA) has been spending the majority of the past week cataloguing the new, removed, and modified components of an upcoming project.
What is the main purpose of the BA performing this work?
- A . To establish the key performance indicators
- B . To define the future state
- C . To identify the domain subject matter expert
- D . To document the current state
Project Communication Management includes the processes required to.
- A . Ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
- B . Identify, define, combine, unify, and coordinate the various processes and project management activities with the Project Management Process Groups.
- C . Manage timely completion of the project.
- D . Organize, manage, and lead the project team.
Which elicitation activity is best described to ensure that the needed resources are organized and available for the elicitation?
- A . Confirming elicitation results
- B . Preparing for elicitation
- C . Planning for elicitation
- D . Managing stakeholder requirements
Which one of the following statements best describes what an assumption is?
- A . These are the things that may restrict the options for the endeavor.
- B . The weather will always be hot in the summer and cool in the winter.
- C . The project must be completed by December 18.
- D . These are things that are believed to be true, but they have not yet been confirmed.
A government agency has initialed a project to implement a customer registry that will be shared
across multiple agencies. Early estimates indicate there will be hundreds of requirements.
While determining the requirements traceability approach, what factor takes precedence?
- A . Number of defects
- B . Cost of tracing
- C . Number of stakeholders
- D . Cost of testing
A business analyst (BA) is working on a project to revise the way a company bills its customers. At the end of the project, the BA creates the following matrix:
- A . Stakeholder analysis
- B . Root cause analysis
- C . Business capability analysis
- D . Strategy analysis