Kendra is the business analyst for her organization. She’s working with the project manager and the project sponsor to discuss the current requirements. Kendra believes it’s important for the project manager to first implement the requirements with the highest amount of risks.
Is this a good idea?
- A . No, the project manager and team should actually implement the lowest risk requirements first.
- B . Yes, if the risky requirements cause the project to fail, the organization will not suffer much loss, as it hasn’t invested much time or money on the project.
- C . No, the project manager and team should implement the requirements with the highest risks last.
- D . Yes, this allows the project manager to get the risky work done as soon as possible in the schedule.
All of the following statements are true regarding a brainstorming session during requirements elicitation except for which one?
- A . All ideas should be visibly recorded.
- B . The number of ideas should not be limited.
- C . The ideas should be generated with a cost or time estimate.
- D . All ideas should be shared without any discussion, criticism, or evaluation.
All of the following statements are true regarding a brainstorming session during requirements elicitation except for which one?
- A . All ideas should be visibly recorded.
- B . The number of ideas should not be limited.
- C . The ideas should be generated with a cost or time estimate.
- D . All ideas should be shared without any discussion, criticism, or evaluation.
There are three inputs to the business analysis planning approach process.
Which one of the following is not one of the three inputs?
- A . Risk and rewards analysis
- B . Business need
- C . Organizational process assets
- D . Expert judgment
One of the techniques to assess capabilities in an organization is to use SWOT.
What does SWOT accomplish?
- A . SWOT reviews your strengths, weaknesses, opportunities, and threats.
- B . It identifies how current capabilities match up against the influencing factors.
- C . It assesses the strength, weaknesses, opportunities, and threats.
- D . SWOT is a goal setting technique that means "Sweat Works Over Time."
You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register.
All of the following information should be included in the stakeholder register except for which one?
- A . Assessment information of the stakeholders‘ major requirements, expectations, and potential influence
- B . Stakeholder management strategy
- C . Stakeholder classification of their role in the project
- D . Identification information for each stakeholder
Complete this statement.are longer-term, ongoing, and qualitative statements of a state or condition that the organization is seeking to establish and maintain.
- A . Objectives
- B . Goals
- C . Requirements
- D . Operations
The business analyst (BA) has documented the requirements for a new system and is preparing the requirements for approval.
Which of the following helps ensure that requirements are fully understood and traceable?
- A . Requirements are extracted for review
- B . Requirements are properly classified
- C . Requirements are validated
- D . Requirements meet regulatory standards
A project is being initiated to create new financial reports for the accounting department, and the accountants have a wide range of views as to what would serve them best.
What should the business analyst (BA) do to develop the correct set of requirements?
- A . Resolve differences of opinion
- B . Conduct an impact analysis
- C . Estimate the scope of work
- D . Perform a feasibility study
A company wants to launch a new product that will have similar features to an existing product. A business analyst (BA) working on the project has invited the product manager to explain the features and business rules of the new product.
Which activity must the BA perform in preparation of the session?
- A . Align the scope of the project to the company’s strategy
- B . Review information about the existing project
- C . Ensure requirements are traceable
- D . Determine the communication plan for requirements