A project team member is confused about why a small change requires the team to look at the different enterprise-level business objectives when a desired state can be achieved easily without this analysis.
What can the business analyst (BA) do to help the team member understand?
- A . When funding is available for extra analysis, the project team needs to use it.
- B . Impact analysis helps gain critical thinking to achieve the desired solution.
- C . Proper analysis from different aspects is required to select the first solution.
- D . Detailed assessments might result in future success of other projects.
You are the business analyst for your organization and you’re working with Fran on business analysis processes. Fran is a stakeholder who wants to ensure that your business analysis approach and activities are compatible with the project activities.
Of the following, what type of business analysis stakeholder is Fran?
- A . Regulator
- B . Project manager
- C . Sponsor
- D . Domain subject matter expert
A client wants to rehire a business analysis consulting firm for another project. The assigned business analyst (BA) developed a good rapport with the stakeholders, but delivered documents that contained lots of technical jargon that the client could not fully understand.
Based on the feedback, the consulting company should:
- A . recommend a new methodology which is the latest trend in the industry.
- B . assign a different BA to the project.
- C . discuss the feedback during the brainstorming sessions after project completion.
- D . identify performance metrics before commencing work.
A business analyst (BA) is working on a project to revise the way a company bills its customers.
At the onset of the project, the BA creates the following matrix:
- A . Stakeholder analysis
- B . Strategy analysis
- C . Root cause analysis
- D . Business capability analysis
A business analyst (BA) is working on a project that has a release date that cannot be changed. The BA engaged with stakeholders and completed the business requirements elicitation task. Upon review with the rest of the project team, it is determined that not all requirements can be implemented by the set deadline.
What must the BA do to ensure maximum business value?
- A . Ensure test scenarios conform to business requirements
- B . Align business requirements to organizational strategy
- C . Analyze requirements to remove unnecessary components
- D . Choose an appropriate format to communicate requirements
In the life of a project, when do the number and impact of change requests often increase?
- A . During project planning
- B . Once the project scope is reviewed
- C . Towards the end of the project
- D . At the launch of the project
An organization’s board of directors has funded a new mobile application to support external customers. The business case was developed with an emphasis on objectives to broaden the organization’s brand and increase customer engagement. The business analyst (BA) is reviewing a group of user stories with the product owner. One of these user stories is:
"As a customer service representative, I need to enter my time on the mobile application so that I can leave work to pick up my sick daughter from school."
The product owner wants to take advantage of this opportunity to provide the staff with a way to enter their time away from the office and create an interface to the Payroll application.
How must the BA evaluate alignment with the existing objectives?
- A . Add the functionality to the list of requirements.
- B . Review business objectives and determine potential value.
- C . Ask the product owner to rank this user story against the existing product backlog.
- D . Suggest that the story be included with a change to the solution scope or be removed.
A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately.
What issue may arise by doing so?
- A . Stakeholders may refuse the solution.
- B . Requirements metrics may not be measurable.
- C . The BA may significantly impact other aspects of the project timeline.
- D . The business need may change.
A business analyst is studying the cost of the endeavor in relation to the projected income the endeavor will bring once the project is completed.
What financial valuation technique can the business analyst use to determine the breakeven point for the project?
- A . Payback period
- B . Average rate of return
- C . Cost-benefit analysis
- D . Discounted cash flow
A long-established company selling ice cream is entering its crucial sales period leading up to summer. Based on the company’s risk tolerance, a business analyst (BA) has advised against replacing the most popular flavors with new untested flavors.
What is the company’s attitude toward risk, as assessed by the BA?
- A . Risk-optimizing
- B . Risk-neutral
- C . Risk-averse
- D . Risk-seeking