Question #140
You have Power Automate Flow to create a flow that automatically sends email to a project manager when project team members mark a task as complete.
Project team members are prematurely marking tasks as complete. You must add quality control into the process by sending an email to a project lead for confirmation that the task is in fact complete before sending the email to the project manager.
You need to modify the flow.
Which component should you use?
- A . a process argument
- B . a condition
- C . an expression
- D . a trigger
- E . an action