ABC is a worldwide fast-food organisation. One of the branches, in downtown Cape Town, decided to implement an ISO 9001 quality management system and you are the audit team leader (with two other auditors) that will carry out the certification audits, Stage 2.
ABC receive the orders by phone or internet; some of the employees deliver the ordered food to indicated
addresses. The normal menu includes 15 different types of hamburgers; however, in the last two weeks,
due to a shortage of a special type of meat, they can only prepare six of the 15 varieties.
During the internal meeting of the audit team, you ask one of the auditors to describe what she has observed. She audited the reception of orders from customers (via phone or internet) and the communication of the orders to the kitchen. She noticed that the menu offering food on the website is still the normal one, with 15 different hamburgers, and during a 30-minute period, she observed many customers reluctantly accepting something other than the hamburger they preferred.
You, as audit team leader, inform the Quality Manager of your concern about the major nonconformity, since you consider this a serious breach of the basic principles of quality that lasted two weeks without action being taken.
Right at the beginning of the Closing meeting, you discuss the nonconformity with the General Manager.
She got quite upset and said she was going to make a complaint to the certification body and left the room; the Quality Manager was the only member of ABC left with the audit team. The Quality Manager said the General Manager would not come back to the meeting.
What would you do? Choose the best from the following options:
- A . Ask the Quality Manager for a break to discuss the issue with the members of the audit team.
- B . Ask the Quality Manager to listen to the nonconformity the auditor will present and continue with the meeting until its closure.
- C . Inform the Quality Manager that the certification process is put on hold and leave the room.
- D . Inform the Quality Manager that you consider the meeting closed, and that you will report to the Certification Body for instructions.
Which two of the following aspects of a quality management system must the organisation continually improve?
- A . Suitability
- B . Adaptability
- C . Effectiveness
- D . Responsiveness
- E . Efficiency
- F . Applicability
XYZ Corporation employs 100 people, and during a Stage 1 certification audit, certain issues are identified with the Quality Management System (QMS).
Which two options describe the circumstances in which you could raise a nonconformity against Clause 6.2 of ISO 9001:2015?
- A . Quality objectives are not being implemented by the organisation’s personnel.
- B . The consultant has not interpreted ISO 9001 correctly.
- C . Establishing quality objectives did not include top management.
- D . Quality objectives were not established in alignment with the organisation’s quality policy.
- E . The organisation cannot afford to undertake quality objectives all at once.
- F . Quality objectives are not maintained as documented information.
DRAG DROP
You are carrying out an annual audit at an organisation that offers home security services. You are interviewing the Quality Manager (QM)
You: "Would you tell me about your management review process?"
QM: "The senior management team plans to review the management system every six months. The review follows a set agenda and records are maintained."
You: "May I see the records from the last two management reviews?"
Narrative: The Quality Manager gives you the latest record, which shows the last management review took place nine months ago.
The Quality Manager then gives you the previous management review record, which took place one year before the latest review.
You: "Are there any other review reports in the last two years?
QM: "No, these are the only ones."
You decide to raise a nonconformity.
To complete the nonconformity report click on the blank section you want to complete se it is highlighted in red and then click on the applicable text from the options below. Alternatively, drag and drop the options to the appropriate blank section.
The following actions need to be carried out during a third-party audit planning stage.
Which two actions correspond to the individual(s) managing the audit program before the involvement of the audit team leader?
- A . Prepare the audit plan
- B . Assign responsibilities within the audit team
- C . Prepare the checklists
- D . Provide the resources needed
- E . Review the reports of previous audits
- F . Select the audit team members
Whistlekleen is a national dry cleaning and laundry company with 50 shops. You are conducting a surveillance audit of the Head Office and are sampling customer complaints. 80% of complaints originate from five shops in the same region. Most of these complaints relate to customer laundry not being cleaned as customers require. The Quality Manager tells you that these are the oldest shops in the company. The cleaning equipment needs replacing but the company cannot afford it now. You learn that the shop managers were told to dismiss most of the complaints because of the poor quality of the laundered materials.
On raising the matter with senior management, you are told that there are plans to replace the equipment in these shops over the next five years.
You raised a nonconformity against clause 8.5.1 of ISO 9001.
Based on the scenario, select the three options which best describe the evidence for raising such a nonconformity.
- A . Customer complaints are not taken seriously by the organisation.
- B . Shop managers were told to make excuses to customers with complaints.
- C . Some equipment used was not suitable for the laundry process.
- D . The management failed in planning to replace obsolete equipment.
- E . The operators did not check the condition of the customer’s product upon receipt.
- F . The operators did not check the laundry before release to the customer.
- G . The organisation failed to control the laundry operations in 5 shops adequately.
- H . The organisation failed to maintain all of its equipment to an adequate standard.
Which two of the following should be included in an audit plan?
- A . List of findings from the last audit
- B . Name of the auditee general manager
- C . Signature of Certification Body Technical Reviewer
- D . Sequence and timings of audit activities
- E . Date of next audit
- F . Name of auditees and auditors
You are an auditor from a construction organisation who is conducting a second party audit to ISO 9001 at a steel rolling mill producing structural steelwork. When auditing the rolling process, you find that the operator who is unloading the furnace does not use the adjacent infrared pyrometer to measure the appropriate product temperature in readiness for the next production stage.
You: "How do you tell when the billet is ready for the rolling stage?"
Operator: "I’ve done this job for 20 years. I can tell by the bright red colour."
You: "What happens if the colour is wrong?"
Operator: "The billet goes back into the furnace."
You: "Is the pyrometer ever used?"
Operator: "Only in borderline cases."
You continue to interview the operator and find that around 25% of the billets are sent back to the furnace. This includes 80% of the borderline cases.
Select three options that would provide evidence of conformance with clause 9.1.1 of ISO 9001.
- A . Periodic analysis of the results of temperature checks.
- B . Certification of conformance to national standards from the manufacture of the pyrometer.
- C . An increase in the use of the pyrometer by operators.
- D . Maintenance plan for the furnace.
- E . A procedure that provides instruction in taking billet temperature.
- F . Planning for monitoring and measuring the billet temperature.
- G . A quality objective to achieve lower recycle rates for billets.
- H . Annual review records for furnace operators.
DRAG DROP
The following are stages of an audit, put them in the order they would be conducted.
The first and last stages have been done for you
To complete the sequence click on the bank section you want to complete so it is highlighted in red and then click on the applicable text from the options below.
Select the term which best describes the quality management system process of modifying a non-conforming product to bring it within acceptance criteria.
- A . Concession
- B . Correction
- C . Corrective action
- D . Preventive action